Sign up to receive notices about road closures and construction – Text CLEELUM to 91896
NOTE: All posted Construction schedules are subject to change as needed.
In Progress…
First Street Downtown Revitalization Project – FINAL PHASE 3D
Map and Brochure
Full Project Plans and Engineering
Full Project Estimated Timeline
3-week Look Ahead Schedule
-
-
- ACI Contractors work a 4-10 M-TH work schedule. This means they will not actively work on Fridays unless necessary.
- Public Works has procured “OPEN DURING CONSTRUCTION” signage for businesses within the current construction zone. These will be posted to new locations as the project progresses.
- Beautification and Façade Grants – Cle Elum Downtown Association
- Please exercise caution in construction zones, following local protocol and laws. Construction areas can be narrow and often have a greater potential for organic debris (gravel, rocks, dirt, etc.) as well as slower traffic that may cause additional travel time.
- REMINDER: Construction schedule is provided as a general notification and guideline. Many factors, including inclement weather, materials and other extenuating factors have the potential to alter the overall schedule have the potential to alter the overall schedule.
- Please direct questions to Aaron Barr: [email protected]
- Construction updates every Thursday:
-
PEOH to BULLITT (NORTH)
BULLITT to WRIGHT (NORTH)
WRIGHT TO HARRIS (NORTH)
PEOH to BULLITT (SOUTH)
-
-
- Bullitt Storm
- September 3 – 6
- Sidewalk Pour
- September 3 – 12
- Bullitt Storm
-
BULLITT to WRIGHT (SOUTH)
-
-
- Paving Prep
- September 12 -16
- Grade curb
- September 5-10
- Pour curbs
- September 11
- Root Barrier
- Starting September 16
- Grade Sidewalk
- Starting September 16
- Paving Prep
-
WRIGHT TO HARRIS (SOUTH)
-
-
- DEMO
- Starting September 16
- DEMO
-
*Dates are subject to change based on current site conditions
- Second Street Pathway Project –
- Second Street Pathway is a 10-foot-wide asphalt pathway that can be used for bikes and pedestrians alike! Each intersection will have a concrete bulb out added on the side of the street that has the pathway. This project includes a new storm drain in the center of the roadway and new catch basins on the side.
- Please direct questions to Aaron Barr: [email protected]
- Full Project Plans and Engineering – Stafford Ave to Short Ave
- The first 5 blocks plans & engineering – Stafford Ave to Wright Ave
- Timeline for the first 5 blocks – Stafford Ave to Wright Ave:
Construction begins 7/8/2024 Estimated Completion – First 5 blocks 9/9/2024 There will be block closures on Second Street while work is occurring within the block and detours as needed. - Second Street closed from Pennsylvania Ave to Harris Ave M-F, local access only, open on the weekends.
Upcoming…
UKC Community Recreation Center – Pending
-
-
- Project information located here: recreationukc.org
- Notice of Application and Environmental Review & Comment Period – link to Public Notices page – please scroll down
-